PPP Projects at Mormugao Port

The Mormugao Port Trust has two PPP projects under operation. These are (i) Multipurpose General Cargo Berth at Berth No. 5 & 6 operated by South West Port Ltd. and (ii) Coal Handling Terminal at Berth No. 7 operated by Adani Mormugao Port Terminal Pvt. Ltd. The outlay of each project is as follows:

S.No

Project

Project Cost

(i)

Multipurpose General Cargo Berth at Berth No. 5 & 6

Rs. 245 Cr.

(ii)

Coal Handling Terminal at Berth No. 7

Rs. 406 Cr.

   

          The nature of agreement and main clauses under the PPP

S.No.

Project

Nature of Agreement

Main Clause

(i)

Multipurpose General Cargo Berth at Berth No. 5 & 6

License Agreement

i.        Minimum Guarantee Throughput (MGT) of 5 MMTPA effective from 66th month onwards from the date of handing over of the Licensed Premises.

 

ii.      Revenue share of 18% on gross revenue.

(ii)

Coal Handling Terminal at Berth No. 7

Concession Agreement

i. MGT fixed for the concessionaire is as under:

Year 1      0.8 MMTPA

Year 2      1.1 MMTPA

Year 3      1.4 MMTPA

Year 4      1.7 MMTPA

Year 5      2.0 MMTPA

onwards

ii. Revenue share of 20% on gross revenue.

 

The information was given by Minister of State for Shipping  Mansukh L. Mandaviya in a written reply to a question in the Rajya Sabha on July 24.